Cowfold roadworks now set to continue into next week

Roadworks on the A272 in Cowfold which were set to be completed this Friday (September 20) have been delayed.
JPCT 100913 S13370066x Cowfold traffic hold-ups, A272 -photo by Steve CobbJPCT 100913 S13370066x Cowfold traffic hold-ups, A272 -photo by Steve Cobb
JPCT 100913 S13370066x Cowfold traffic hold-ups, A272 -photo by Steve Cobb

West Sussex County Council (WSCC) have issued an apology after discovery of old abandoned pipes and a water tank underneath the carriageway has set the estimated completion date back until Wednesday (September 25).

Extra help has been drafted in to finish the maintenance currently being done at the Coach House roundabout, Cowfold.

Hide Ad
Hide Ad

A Spokesperson for WSCC said: “Essential drainage works are being carried out to alleviate flooding problems which have affected the area.

“Extra gangs have been drafted in by contractor Balfour Beatty and everyone will be working over the coming weekend to finish the project.”

The also state that two new manholes need to be built in the road.

Weather permitting, the County Council will complete the work affecting the carriageway by Wednesday, September 25,” they continued.

Hide Ad
Hide Ad

Balfour Beatty will control the temporary traffic lights manually, which have been in place since Monday September 9, during peak hours to help ease the flow of traffic.

Despite the work starting on August 12, traffic delays hadn’t been an issue until the introduction of the lights.

The spokesperson continued: “The County Council apologises for any inconvenience caused to motorists and residents by the roadworks.

Drivers are advised to allow for extra time on their journeys or seek an alternative route.”

What are your thoughts on this issue? Has the work affected you or your journey?