Sewer pipe work set to continue in Chichester

The next phase of construction work for a new 10km sewer pipeline in Chichester is set to begin this month.
Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143806001Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143806001
Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143806001

‘Scores of people’ interested in the £22.1 million scheme went to a public drop-in session at Chichester Baptist Church in February. Another session had been planned for Graylingwell this month but has had to be cancelled because of the Covid-19 lockdown. 

The next stage of Southern Water’s construction work will start from April 20.

Hide Ad
Hide Ad

A spokesman said: “A site team will be working at the junction with St Paul’s Road and Norwich Road, for approximately 100 meters towards Worcester Road, and other works starting from this week will take place at Kingsmead Avenue.

David Winterburn, Senior project manager, Southern Water.Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143733001David Winterburn, Senior project manager, Southern Water.Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143733001
David Winterburn, Senior project manager, Southern Water.Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143733001

“Letters have recently been sent to local residents to confirm details of this work, and to kindly request that this area is kept clear of parked vehicles from April 20.”

Plans for the pipeline and pumping stations were given planning permission by West Sussex County Council in September 2018.

David Winterburn, senior project manager, said: “First of all, thank you to everyone who attended our public event at Chichester Baptist Church last month, feedback on our plans is essential.

Hide Ad
Hide Ad

“We are now in an extraordinary time and as key workers, we continue our planned essential works for this pipeline, but of course adhering to very strict rules – we ask people to be mindful of this.

Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143817001Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143817001
Residents inspected the plans to build a new sewer in Chichester. Pic Steve Robards SR2002283 SUS-200228-143817001

“The new pipeline and pumping stations will provide essential wastewater services to the wider community.”

Works to set up a site compound in St Paul’s Road, which began in early March, are expected to be completed ‘over the next four weeks’.

The spokesman added: “The pipeline and pumping stations run from the west of Chichester to Tangmere wastewater treatment works, in an arc to the north of the town.

Hide Ad
Hide Ad

“This will serve around 4,000 homes in key development areas around Chichester.

“The scheme started in June 2019 and construction of the new pipeline is planned to be complete in August 2021, with the whole project concluding in 2021.”

To date, around 6km of pipeline has been installed between Tangmere Wastewater Treatment Works and Westhampnett Wastewater Pumping Station.

Work to build the pumping station at Westhampnett and Tangmere are also said to be ‘progressing well’. 

Read More
Works for new £22 million Chichester underground wastewater pipeline to start in...

A message from the Editor, Gary Shipton:

Hide Ad
Hide Ad

In order for us to continue to provide high quality and trusted local news, I am asking you to please purchase a copy of our newspapers.

With the coronavirus lockdown having a major impact on many of our local valued advertisers - and consequently the advertising that we receive - we are more reliant than ever on you helping us to provide you with news and information by buying a copy of our newspapers.

Our journalists are highly trained and our content is independently regulated by IPSO to some of the most rigorous standards in the world. But being your eyes and ears comes at a price. So we need your support more than ever to buy our newspapers during this crisis.

Stay safe, and best wishes.