These pictures taken on Tuesday (November 24) show that the windows by the pavilion's staircase have been removed.
Scaffolding has been erected to the side and security fencing has closed off the area while the revamp works are carried out.
The venue announced at the end of July that works would be carried out.
Specialist heritage contractor Associated Steel Window Services (ASWS) is refurbishing the pavilion's staircase glazing to help preserve the Grade I listed Modernist building.
The DLWP opened in 1935 and was designed by architects Erich Mendelsohn and Serge Chermayeff.
A DLWP spokesperson said the work is part of a project, called An Icon For Everyone, in partnership with Rother District Council and Haworth Tompkins architects.
They said work is being carried out because the north and south staircases are in disrepair.
Cracks in the curved glass windows are expanding with every storm and many of the original metal-framed, single-glazed windows show signs of corrosion and cracking, resulting in poor airtightness, the spokesperson said.
The spokesperson added that ASWS is refurbishing both bowed-plan staircase steel frame windows.
As part of the works, the windows have been removed and transported to ASWS's Surrey workshop for repair and restoration, alongside the installation of new steel ring beams, curved metal beading and new glazing, the spokesperson said.
The café and first floor remain open during the staircase works and will be fully accessible via the lift and the north stairs, they added.
Stewart Drew, CEO and director, De La Warr Pavilion, said: “From local residents to visitors from across the world, people are often drawn to the De La Warr Pavilion’s distinctive modernist staircases. However, decades of use and exposure to the harsh coastal environment have led to deterioration, including cracked glazing and ageing materials.
“We are delighted to be working with specialist steel window experts, ASWS, to restore and upgrade the staircase glazing. These improvements will not only enhance the visitor experience and preserve an iconic element of the pavilion’s modernist design, but also improve the building’s performance, increase its long-term resilience and reduce its operational environmental impact.”

5. The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone".
The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone". Photo: Staff

6. The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone".
The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone". Photo: Staff

7. The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone".
The De La Warr Pavilion on November 24 2026 with all of the staircase glazing removed during a major phased transformation project called "An Icon for Everyone". Photo: Staff