Bognor Regis theatre refurbishment continues to make 'steady progress', Council says

£15 million works on Bognor’s Alexandra Theatre continue to make ‘steady progress’, according to Arun District Council

The project, which will increase the number of seats in the main auditorium, introduce five new flexible studio spaces, a modern cafe and more, is expected to finish in Mid-2026 and contractors at Neilcott Construction say things are progressing right on schedule.

Image: Arun District Councilplaceholder image
Image: Arun District Council

Recent progress highlights include:

  • The reinforced concrete slab at first floor level is now being completed in two phases. The first section was successfully poured on 9 September, with the second section scheduled to be poured between 12 and 15 September, subject to weather and site conditions. This is a key structural milestone in shaping the new layout of the building
  • Shuttering and steel installation: steel reinforcement and shuttering (temporary moulds) were installed in preparation for the first-floor slab pour.

  • Roof dormer works underway: work has begun on forming the dormers along the west side of the auditorium roof. These features are part of the building's heritage-sensitive reconfiguration and will support ventilation and natural light.

The next steps, meanwhile, include

  • RC frame: construction of vertical columns and structural walls will progress from the new first-floor slab up to the underside of the roof
  • ongoing roof works: the team will continue forming the dormers along the west-facing slope of the roof
  • internal building works to progress: builders will begin works inside the existing building, including the main auditorium and newly created Studio 5 space.

"The project remains on track and continues to be delivered in line with the agreed construction programme. Health and safety standards remain a top priority, and the site continues to operate securely with minimal disruption to the surrounding area,” a spokesperson for Arun District Council said.

The full project, which started in Spring last year, is intended to improve arts, culture and community offerings throughout Bognor Regis, and Arun District Council says it should work in tandem with ongoing upgrades to the promenade, the Arcade and the now-finished Place St Maur project, to make the town an even more attractive destination for residents and visitors alike.

The £15 million budget was pulled from Arun District Council’s share of the Levelling Up Fund, plus an additional three million from the council itself and a further £94,290 from the UK Shared Prosperity Fund.

Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice