Busy Hastings route to be hit by roadworks until 2028

Roadworks are set to start on the Ridge at Hastings in a project that will take until 2028 to complete.

Southern Gas Network (SGN) has sent out letters notifying residents in the area of the work which will be delivered in phases.

It is replacing century old mains and service pipes with modern plastic equivalents.

A spokesperson for SGN said: “As we work along the road we will link the new main with existing pipework in nearby side roads, ensuring a safe and reliable gas supply for local homes and businesses.

"For everyone’s safety we will be using temporary traffic lights throughout. We know that this is a traffic sensitive route so we will have an operative on site to adjust timings to help with traffic flow. However, we'd recommend motorists allow extra time for journeys while the lights are in operation.

"We recognise roadworks can be frustrating. However, the new plastic pipe has a lifespan of 80 years. This means that once our essential upgrade project is complete, Hastings residents and businesses will be able to enjoy the benefits of a safe and reliable gas supply for many years to come.”

Phase one of the work will be starting on Tue, Sep 22, 2026 with work taking place between the junctions with Grange Road and Stonestile Lane Engineers will be replacing 1500m and upgrading 30 services to adjoining properties. This should hopefully be finished by Fri 11 December 2026.

Phase 2 will start on Monday, January 4 ,2027, working between the junctions with Stonestile Lane and Elphinstone Road. This is expected to be finished by Monday 5 Apr 2027.

Phase 3 will start on Monday, June 28, 2027 working between the junctions of Elphinstone Road and Norcross Close, expected to be finished by Monday 13 September 2027.

Phase 4 will start on Saturday, October 16, 2027 working between the junctions with Grange Road and Stonestile Lane. This will hopefully be finished by Sunday 31 October 2027.

Phase 5 will start on Monday 3 January 2028, working from opposite Maitland Close, past Hillside Road and Beany's Lane, to just short of the Conquest Hospital roundabout. This is expected to be complete by Monday 28 February 2028.

The final phase will begin on Monday 26 June 2028, working between Norcross Close just past the junction with Pine Avenue. This is expected to be finished on Monday 21 August 2028.

People can sign up for updates on the work on the SGN website.