Hastings Borough Council said it is taking enforcement action against a developer regarding the derelict site of a former amusement arcade destroyed by fire.
In December 2025, it urged Oasis Developments Hastings Ltd to start work on the site at 39-41 George Street in the Old Town.
The developer submitted an application for permission to build 20 flats, six holiday lets and four commercial units.
A council spokesperson said: “We recognise the continued concern regarding the condition of the site and understand residents’ frustration that there has been no visible improvement since previous assurances were given.


“The council wrote to the owner in December to provide an opportunity for the necessary works to be carried out voluntarily. As those improvements have not been delivered, the council has now begun the formal planning enforcement process.
“A Section 215 notice has been issued to the owner requiring the condition of the site to be addressed.
“The owner has 10 working days to respond to the council’s correspondence.
“If no satisfactory response is received, or appropriate action is not taken, the council will consider the use of its powers under the Town and Country Planning Act 1990 to take further enforcement action.
“We appreciate that the lack of visible change is disappointing for residents. However, the council must follow the correct legal processes to ensure that, if further escalation becomes necessary, any action taken is robust and legally sound.”
A Section 215 notice is a power local authorities use to require landowners/occupiers to clean up land or buildings that adversely affect the local area's amenity. It specifies required works and a minimum 28-day compliance period, often used for issues like overgrown gardens, waste, or broken windows.
The blaze at the former amusement arcade and nightclub in George Street broke out on January 18, 2023.
Firefighters and 10 pumps spent all night tackling the blaze. Sussex Police said the fire was being treated as ‘deliberate ignition’.
Work to knock down the building started in April 2023 and demolition was completed in August that year.
The three-storey building was previously an amusement arcade and a nightclub.
The building was sold for redevelopment into 20 flats in November 2022.
A statement from Oasis Developments Hastings Ltd said: “It is not correct to suggest that the prolonged delay at 39–41 George Street is solely the responsibility of Oasis. A significant part of the delay has arisen from the planning process and the time taken for the council to determine the application, which is still pending.
“As agreed with the council in December 2025 to conclude matters, the requisite report was submitted, and we are now awaiting planning approval from the council.
“We have now been waiting for planning for many years. Had the consent been granted within a reasonable timeframe, the construction works could have been completed by now, which would have significantly reduced the losses we have continued to incur. The prolonged delay has had a serious financial impact on us.
“In December we took steps to improve the site, including tidying the lower level, removing weeds and making good parts of the hoarding. We have also been working with local traders regarding further hoarding improvements with visuals, and that remains in progress.
“In our view, the Section 215 notice is not necessary in these circumstances as we have been waiting for planning. The building element referred to is due to be demolished as part of the proposed development, so it is neither practical nor cost-effective to carry out repair or temporary covering works simply to make it good for a short interim period.
“Oasis remains committed to delivering the scheme and respectfully asks the council to issue the planning approval so that the project can move forward, construction can begin, and this long-running situation can finally be brought to an end.”
The council disputed Oasis’ claim that the authority had caused a delay.
A spokesperson said: “Planning Committee previously resolved to grant planning permission for redevelopment of the site, subject to completion of a legal agreement and viability matters. The council has therefore not delayed the determination of the application.
“The Section 215 notice is a separate matter and relates solely to the condition of the site.”