New Bexhill hospital takes shape as opening date for 54-bed facility announced

A new 54-bed hospital in Bexhill is starting to take shape, as building work progresses.

Work on Combe Valley Hospital, a facility for adults and older people with mental health conditions, started more than two years ago, with a ground breaking ceremony taking place on January 30, 2024.

The hospital, on Mount View Street, is being developed by Sussex Partnership NHS Foundation Trust with NHS Sussex. It is being built in partnership with Kier Construction.

Building work has taken place throughout this year, with the new hospital expected to welcome its first patients in November, Kier said.

The new Bexhill hospital is taking shapeplaceholder image
The new Bexhill hospital is taking shape

In its latest update, the company said: “Out-of-hours working on the Combe Valley site is beginning to pay dividends with progress on the internal areas progressing well. Many ward bedrooms have now been decorated and lighting installed. This has been carried in conjunction with vinyl floors being laid and doors installed.

“Furniture and fittings to be installed by Kier continue to arrive on site. These have included the fittings for bedrooms and ensuite bathrooms.

“The lift has been commissioned and is operational. Staircases at the north and south of the building have been boarded up. There is also now a lot of ‘snagging’ activity being undertaken to ensure that all areas are fit-for-purpose.”

Snagging is the process of inspecting a newly built or renovated property to find and list minor defects, unfinished work, or cosmetic damage before the final handover

The new Bexhill hospital is taking shapeplaceholder image
The new Bexhill hospital is taking shape

Kier said South East Water has completed connections to the site for drinking water, surface water drainage, and foul drainage.

Telephone and broadband connections have also been completed, Kier added.

A spokesperson said: “We are ramping up our efforts to make sure the hospital is up and running so we are ready to greet patients in November.”

Building work on the new hospital was initially delayed.

An aerial image of what the hospital will look like once building work is complete. Picture: Sussex Partnership NHS Foundation Trust/Kier Constructionplaceholder image
An aerial image of what the hospital will look like once building work is complete. Picture: Sussex Partnership NHS Foundation Trust/Kier Construction

In January 2025 Sussex Partnership NHS Foundation Trust said construction work was due to be completed in autumn that year.

A trust spokesperson said the delay was caused by 'significant challenges, including exceptional rainfall during critical project stages and a major subcontractor insolvency'.

The hospital was officially named Combe Valley - a name chosen by staff and service users.

The spokesperson added: “The hospital will replace the outdated inpatient services currently provided in the Department of Psychiatry at Eastbourne District General Hospital.

“It will remove outdated dormitory accommodation, replacing the shared wards with individual bedrooms, each with en-suite bathrooms, provide a modern and improved therapeutic environment for patients, and create enough capacity to meet future inpatient needs.

“This represents the first step in a wider programme aimed at building new modern facilities on a single site which will, in the future, meet all mental health inpatient needs for the people of East Sussex and beyond.”