Worthing Heat Network expansion to continue without road closures

Work to reinstate parts of Steyne Gardens and continue the rollout of the Worthing Heat Network began this week.

The Worthing Heat Network, officially launched in February, is designed to provide low-carbon heating to key buildings across the town, with the first phase already operational in several landmark sites.

In an update on May 15, the developer Hemiko thanked residents, businesses, and visitors for their patience while plans to connect the network to Splashpoint Leisure Centre and the Pavilion Theatre were finalised following updated ground investigations.

The company said that from Monday, May 18, sections of Steyne Gardens will begin to be reinstated so that the ‘ground can recover and the grass can regrow’, allowing part of the gardens to be reopened for public use.

The Worthing Heat Network, officially launched in February, is designed to provide low-carbon heating to key buildings across the town, with the first phase already operational in several landmark sites.  Photo: Elaine Hammondplaceholder image
The Worthing Heat Network, officially launched in February, is designed to provide low-carbon heating to key buildings across the town, with the first phase already operational in several landmark sites.  Photo: Elaine Hammond

At the same time, construction teams will prepare for the installation of underground pipework in a reduced working area in the northern section of the gardens.

Hemiko explained that, rather than digging trenches across Brighton Road and Steyne Gardens, engineers will use underground drilling techniques to install pipework between the High Street Multi-Storey Car Park and Steyne Gardens.

“We appreciate that the community is eager to see Steyne Gardens returned for public use as soon as possible,” the company said.

“These activities will take place between May 18 and June 25.

Inside the new Energy Hub for the Worthing Heat Network. Photo: Elaine Hammondplaceholder image
Inside the new Energy Hub for the Worthing Heat Network. Photo: Elaine Hammond

“We are committed to completing works and restoring and vacating the gardens ahead of Armed Forces Day to ensure the town centre’s key events can continue as normal.”

The developer also sought to reassure the public that disruption would be kept to a minimum during the next stage of the works.

“Traffic will continue to flow as usual, no road closures are planned, and the High Street Multi-Storey Car Park will remain open throughout the works,” Hemiko said.

“Much of the activity will involve underground drilling to minimise disruption at surface level.”

Residents with questions about the project can contact the company by email at [email protected].

After the official launch in February, we asked the developer a series of questions to explain the value of heat networks and how they work.

Who are Hemiko?

The leading heat network utility provider Hemiko is investing in low carbon heat networks, building them and operating them in Westminster, Worthing and Old Oak & Park Royal.

What are heat networks?

This district heating system works by collecting unused heat from the air, or generating heat at scale, then distributing it as hot water to local users via a network of underground pipes for heating and hot water in buildings.

Has it been done before?

Heat networks are common in major towns and cities across northern Europe and Scandinavia, particularly Copenhagen. They use a heat exchanger instead of a boiler, so there is no need for gas.

What's so good about it?

Heat networks are the cheapest, smartest way to provide clean heat to homes and businesses in the UK. They collect local wasted heat from the air, which reduces the need for foreign fuel imports.

Does it affect air quality?

Yes, because they replace old gas boilers, reducing exposure to nitrogen oxides and sulphur dioxide pollution.

Will it save money?

Heat networks are the most cost-effective way to supply heat to buildings. They draw on local sources of heat, using the most appropriate source at any one time to provide heat to the network.

Who is using Worthing Heat Network?

The Connaught Theatre was the first Worthing building to go live on the network, on September 29, 2025, closely followed by the Worthing Town Hall complex, including the Assembly Hall, plus Worthing Museum & Art Gallery and Portland House. Worthing Hospital has been connected to the heat network and will fully switch over shortly.

What happens now?

The next phase of work will see Splashpoint Leisure Centre and the Pavilion Theatre connected to the network.

What about people's homes?

The pioneering district heating project will eventually supply clean, local heat to buildings and homes across the town. The ambition is to offer this greener, cheaper heat to the whole of Worthing by 2050.

What has it all cost and who paid for it?

Worthing Borough Council was awarded more than £7million of grant funding after a successful application to the government's Public Sector Decarbonisation Scheme. This unlocked £40million of investment from Hemiko, which also plans to invest around £500million by 2050 as the network expands.

The council was required to match-fund the grant with a £3.2million investment towards modernising the public buildings, including new windows for the museum and theatre.

The NHS received approximately £19million in funding from the government to connect Worthing Hospital to the heat network.