Solar panels at Ford Materials Recycling Facility to cost £1.14m
West Sussex County Council is to spend £1.14m installing solar panels at the Ford Materials Recycling Facility.
The allocation of capital funds to the project, was approved on Tuesday (March 24) by Deborah Urquhart, cabinet member for environment & climate change.
The council will now look for a contractor to install hundreds of panels, with a capacity of 570 kWp, which can be expected to generate between 480,000 and 627,000 kWh (units) of electricity per year.
That’s enough to power roughly 370 homes for a year.
A report from Wayne Lewis, the council’s service director for environment & public protection, said the panels will only be fitted on the south-facing rooftops, which will give a higher yield than using all roof surfaces.
A Power Purchase Agreement (PPA) with Biffa, which operates the site under a PFI contract, will be arranged to formalise the sale of power generated by the system.
The report added: “The PFI contract with Biffa will expire in 2033 and so a new PPA will need to be agreed with the subsequent site occupier.
“This system is predicted to cost £1.14m in capital funding and, over its 25-year life, is expected to generate £2.5m gross revenue – £438,000 net when operation and maintenance costs are also considered.”