Worthing Pier repair work progresses as damaged pile removed
Work to repair storm damage to Worthing Pier has moved forward, with contractors removing a cracked supporting pile as part of a wider permanent repair programme.
Worthing Borough Council has been working with structural engineers, Mackley and HOP Consulting, over recent months.
They have been developing plans for the long-term restoration of the storm-damaged section of the pier.
A temporary steel support structure was installed beneath the pier in October 2024 after severe weather caused damage to several of its supporting piles. The structure was introduced to 'give it extra strength', while permanent repair options were assessed.


Following the initial damage, one broken pile was removed immediately in 2024 to prevent further impact on nearby supports. A second adjacent pile was later found to have a crack spanning around two-thirds of its circumference.
That cracked pile has now been removed by contractors as part of the permanent repair scheme, allowing it to be replaced.
Worthing Borough Council said in a Facebook post, on May 13, that the temporary measures have continued to perform as intended while longer-term work is prepared.
The council stated: “The support structure is continuing to do its job so, as part of the permanent repair project, our contractors have now removed the cracked pile so that it can be replaced.”


Looking ahead, the main repair programme is expected to take place during the summer and autumn, when weather and tidal conditions are more favourable for construction work.
The timing is also intended to help reduce costs and disruption, while keeping the pier open where possible.
The council added that it will continue to provide updates as the project progresses.