Piling works underway in project to replace A259’s Exceat Bridge over River Cuckmere
Piling works are now underway in a project to replace a bridge that forms part of the A259 between Seaford and Eastbourne.
The current Exceat Bridge, which goes over the River Cuckmere, is being replaced with a new two-lane bridge to the north of the current site to improve traffic flow.
The plan is for better footways, viewing platforms and a shared space outside the Cuckmere Inn.
East Sussex Highways’ latest update at live.eastsussexhighways.com said: “Vegetation clearance is now completed on both sides of the Cuckmere River. We are now driving columns into the ground in preparation for the bridge foundations to be built (piling works). We expect the sheet piling to be completed by mid-August.”


East Sussex Highways also said the project has been receiving ‘intermittent deliveries’ of the piles to site and said there is ‘increased movement of materials and vehicles’ from the west to the east side of the river.
The update said: “We have also started constructing the main site compound following the completion of archaeological works. This will provide more storage space for materials as construction gets underway.”
In June, East Sussex County Council (ESCC) said ancient pottery, which is believed to be Bronze Age, Iron Age and Roman, was discovered in trenches at the site. ESCC said archaeologists were working on the site before construction to make sure any historical items were recorded and preserved.
Piling is now set to continue on the west side of the river until the end of August.
East Sussex Highways also warned of ‘some disruption’ as heavy machinery and materials are transported to the site under ‘specific road movement orders’.
East Sussex Highways said it held a monthly stakeholder meeting on Wednesday, July 22, to provide updates, talk about milestones and explain technical and logistics concerns. The update said: “We also shared the meeting slides with stakeholders who could not attend.”
Its next stakeholder meeting will be held at the end of August.
People can find out more at live.eastsussexhighways.com.