Bognor’s Alexandra Arts Centre moves closer to completion ahead of 2027 opening
Work on the new Alexandra Arts Centre in Bognor is continuing, with the building now weather-tight and construction moving towards the internal fitting-out stage ahead of its planned Spring 2027 opening.
In an update on November 12, Arun District Council stated progress had been made on both the inside and outside the building, with the removal of scaffolding on its eastern side revealing more of the refurbished exterior.


External work includes the installation of decorative feature banding up to first-floor level, while the first phase of brickwork has been completed. Contractors are now working on the upper sections of the building.
Much of the current activity is taking place inside, where work on the main auditorium includes the installation of acoustic panelling, stage lighting and audio-visual equipment.
Elsewhere, contractors are carrying out plastering, decorating and flooring, alongside ceiling installation and the fitting of skirting and window boards. Work has also started on the public toilet facilities.
Internal scaffolding is being removed as sections of the building are completed, while preparations are under way for the installation of handrails and balustrades.
Mechanical and electrical work is continuing alongside the finishing stages. This includes the installation of heating, ventilation and air-handling systems, as well as ongoing fire safety work. Equipment is also being fitted in the building's plant rooms.
A spokesperson for Arun District Council said: “The outside of the building is close to its final appearance and attention is now firmly on the interior, so these activities will continue across the building in the run-up to Christmas.
"The team remains on track, and we look forward to sharing further updates as the Spring 2027 opening draws closer.”