A new raised car park could be installed at Tesco in Bognor Regis as part of a bid to tackle the flooding problem that leaves the store forced to close.
An application has been submitted to Arun District Council for the installation of a single storey raised car park deck at the Shripney Road superstore together with site alterations, car park reconfiguration, new access into the car park, drainage alterations, creation of new drainage outfall, landscaping and other associated works.
A design and access statement prepared by Inspire Design Limited on behalf of Tesco Stores Ltd said: “The aim is to provide long-term protection to key parts of the site, including the access road and car park, to ensure that the store can continue to service the community during future flood events.”
It said: “The Tesco car park has been severely impacted by increasing flood events, including major incidents linked to Storm Ciaran and Storm Babet in late 2023, followed by a separate event in February 2024. All occurrences were significant enough to cause multi-week store closures, suspension of home deliveries, and the closure of the petrol station and pharmacy.”


The store opened in August 1988 and is situated next to the main Aldingbourne Rife river, within the Environment Agency's Flood Zone 3, which indicates a high probability of river flooding.
“The cause of the flooding is complex and multi-faceted, involving fluvial, sewer, and surface water components,” the statement said. “The primary source is the site's proximity to the Aldingbourne Rife, which frequently reaches overspill capacity during heavy rainfall.
“West Sussex County Council initiated a formal Section 19 Flood Investigation into the 2023 events.
“The increasing frequency and impact of flooding on this floodplain location are a growing concern.”


The site access, store and store entrance are above the highest known flood level.
“The core proposal involves constructing a single-storey car parking deck that will span the entire length of the main store frontage, extending to meet the existing distribution road that runs parallel to the water course,” the statement said.
“A new distribution road is proposed along the store frontage, featuring two shallow access ramps located at either end of the car parking deck.
“Operational analysis has established a requirement for at least 350 spaces during standard trading and a core capacity of 190–210 spaces during flood events. The existing car park currently provides 504 spaces (including 25 accessible and 25 Parent & Toddler bays).


“The new proposal introduces a decked area for 191 spaces (22 accessible, 18 parent and toddler) alongside 273 standard remaining spaces at grade, resulting in a total capacity of 464 spaces. While this represents a net loss of 39 spaces compared to the current layout, the primary benefit is the guaranteed availability of 191 flood resilient spaces, ensuring the store remains functional at all times.
"Furthermore, accessibility has been prioritised over the maximisation of total parking numbers. To enhance ease of use, the parking bays within the decked structure have been increased to a width of 2.7m.
"The void beneath the deck is purposefully sized to continue flooding, thereby ensuring the existing flood water storage capacity is maintained. The void will be enclosed using access grids designed to allow flood water to go through but keeping the void free of obstruction and deter wildlife.
“Furthermore a stringent maintenance and cleaning regime using remote controlled cleaning machines will be implemented to prevent debris accumulating. The proposals utilise part of the disused bus stop area to create the new southern access ramp up to the raised deck.