Worthing’s £49m medical centre still unopened nearly three years on - what we know so far

Worthing’s long-delayed state-of-the-art medical centre will not be ready to open by the end of the year, with the project now expected to take more than three decades to break even financially.

Construction on the Worthing Integrated Care Centre (WICC), in Stoke Abbott Road, began in March 2022, with an initial budget of nearly £34million.

The project was hit by several delays and was declared practically complete in December 2024 – a year after its original target completion date.

NHS services were invited to start moving in during January 2025. However, the discovery of legionella bacteria – which can cause Legionnaires’ disease, a potentially serious lung infection – in the building’s water system put these plans on hold.

Worthing Integrated Care Centreplaceholder image
Worthing Integrated Care Centre

Contractor Galliford Try undertook remedial work, and the bacteria was thought to have been eradicated. But independent testing commissioned by Worthing Borough Council detected traces of legionella two months later.

Several deadlines for handing back the water system have subsequently been missed, according to a document discussed by Adur and Worthing councils’ joint strategic committee. The authority said it would not accept responsibility for the system until it can be demonstrated to be fully safe and functional.

The council document suggested the system could potentially be handed back by the end of 2026, although this was dependent on the scope of works still required. The council has now told the Worthing Herald this target is no longer achievable.

Meanwhile, the project's budget has increased from £33.9million to £48.9million.

The inability to fully occupy the building has ‘created significant shortfalls in rental income and service charge recovery’, while increased costs have also been incurred through additional borrowing, according to the council.

It is now expected to take 35 years of full operation to break even financially, compared to an earlier forecast of 26 years.

Galliford Try remains responsible for resolving the problems with the water system. In early November 2026, the council said the contractors were ‘still working through the issues with the building’. Galliford Try has reportedly commissioned ‘additional expertise’ regarding their installation of the water system, while the council ‘continues to consider all legal remedies available for recovery of losses incurred’.

Once open, the centre will bring together GP services run by Worthing Medical Group, dental services from Sussex Community NHS Foundation Trust and mental health services from Sussex Partnership NHS Foundation Trust, alongside a pharmacy.

There is still no confirmed opening date for the centre.