Rail disruption to affect Sussex passengers as Portsmouth Direct Line upgrades continue

Rail passengers across Sussex are being warned of significant disruption later this month, as Network Rail carries out the next stage of a major upgrade to the Portsmouth Direct Line.

From Saturday, March 28 to Thursday, April 2, buses will replace trains between Havant, Fareham and Portsmouth Harbour – impacting journeys for commuters travelling from coastal towns including Bognor Regis and Chichester.

Network Rail explained that the work is part of a wider £120 million investment to modernise the line, which is used by many Sussex passengers travelling towards Portsmouth and connections beyond.

During the closure, services will be altered across the region.

Southern train passing over Havant level crossing. Photo: Network Railplaceholder image
Southern train passing over Havant level crossing. Photo: Network Rail

Southern trains that usually run to Portsmouth Harbour will instead terminate at Havant.

Services from the south coast will be diverted, with trains that normally serve Portsmouth & Southsea running to Bognor Regis instead.

South Western Railway and Great Western Railway services will also be cut back, starting or ending at Havant or Fareham.

Rail replacement buses will run frequently, including up to five per hour between Havant and Portsmouth Harbour, stopping at key stations along the route.

Passengers travelling from Bognor Regis and Chichester towards Portsmouth are being advised to allow extra time and check before they travel.

Network Rail engineers will carry out a range of upgrades in the Havant and Portsmouth area, including repairs to signalling equipment, track renewals, and structural work on the Portcreek Viaduct.

The improvements follow an earlier £129 million phase completed in 2025 between Farncombe and Petersfield.

Tom McNamee, infrastructure director – speaking on behalf of Network Rail and South Western Railway – said the upgrades are essential to improving reliability for passengers across the south coast.

“Following the successful completion of the first phase of upgrades last year, we are now starting the next stage of modernising signalling on the Portsmouth Direct Line,” he said.

“Some of the signalling equipment in the Havant area is ageing and is increasingly prone to faults. Replacing it with modern technology will improve reliability and help reduce delays for passengers travelling to and from the south coast.

“Some of this work can only take place when trains are not running, so access is carefully planned to complete as much of the improvements as possible while minimising disruption.”

Passengers should also be aware that further engineering work is planned over the late May Bank Holiday, with additional closures expected in the autumn.

Network Rail says the full upgrade programme is due to be completed in 2028, when signalling will be controlled from the Basingstoke Rail Operating Centre, helping improve response times and reduce delays across the network.

For now, Sussex passengers – particularly those in Bognor Regis and along the coastal route – are being urged to plan ahead during the six-day disruption.